responses. Individual names altered for privacy purposes. The information contained in this website is provided for informational purposes only and should not be construed as a forum for customer support requests. Any customer support requests should be directed to the official HCL customer support channels below:
We are currently running Domino 6.5.6 on a small cluster of mail servers.
We are considering an upgrade path of creating new 8.5 servers in the domain, and then migrating users onto the new servers, rather than upgrade the existing servers in place.
Are there any particular issues with this sort of upgrade path?
What would be the order of operations and upgrades for this path? (i.e. when do we upgrade the directory design, etc?)
Feedback response number WEBB7V9R2V created by ~Pippy Opjumivitchjip on 08/25/2009